National Oilwell Varco
ISSUE: Production process took six weeks and costs were high.
SOLUTION: Mapped the process, identified inefficiencies and led a complete improvement programme.
TOOLS USED:
-
Process mapping
-
Lean + Six Sigma (DMAIC)
-
Jig + tool design
RESULTS: Cycle time reduced from 6 weeks to 1 week and First-time pass rate increased from 66% to 98%

Kohler Mira Showers
ISSUE: Low FTPR, yield and equipment efficiency.
SOLUTION: Led a structured improvement programme using
Industry 4.0 and digital manufacturing solutions.
TOOLS USED:
-
8D, Gemba Walks
-
ANDON
-
Value Stream Mapping
RESULTS: 1FTPR improved from 60% to 95%, yield from 45% to 92% and OEE from 52% to 68%.